Emergency ordinance2025-419

Authorize City Attorney to settle lawsuit related to construction of the Streetcar approach ramp located near SE 2nd Ave and accept lump sum payment in the amount of…

The path so far

Each stop is a meeting in the official record, with the City’s own words for what happened.

  1. PassedMeeting guide
  2. Where it standsFinal Council action complete
  3. After the decisionFollow-through is not tracked yetA final vote is not the same as the work being done.

In brief

From the official impact statement

This Ordinance settles a lawsuit brought by the City against Tri-County Metropolitan Transportation District and Stacy & Witbeck, Inc. for defects related to the construction of an on-grade approach ramp for the Streetcar system located at SE 2nd Avenue.

Official impact statement

Decision details

From the official record
Who is affected

This Ordinance settles a lawsuit alleging breach of contract and negligence against parties who performed design and construction services for the ramp project. No public involvement or input was sought regarding this Ordinance. The City Attorney's Office and City Administrator have concluded that it is not appropriate to have public involvement in settlement negotiations regarding lawsuits on behalf of the City.No future public involvement is anticipated or necessary. Approval by City Council of this Ordinance will fully settle the lawsuit in favor of the City of Portland.

Official community impact statement
Financial impact

This legislation will have no impact on City revenue.The City will receive a lump sum payment on behalf of all defendants in the amount of $7.5 million, allocated for repairs for this structure. This Ordinance does not amend the budget.

Official financial impact statement
Prosper Portland analysis

An Economic and Real Estate Development Impact Analysis was not submitted for this proposed action. Pursuant to City Council Resolution 37664, Prosper Portland staff has reviewed the action and agree that it does not require an Economic and Real Estate Development Impact Analysis.

Economic and real estate development analysis, provided by Prosper Portland
City Budget Office analysis

This settlement will bring in $7.5 million to the City, which is the estimated cost of the required repairs. Therefore, there is zero net financial impact of this settlement for the City.

Financial and budget analysis, provided by City Budget Office

Recorded action

Sources & history

Documents1

Official title: *Authorize City Attorney to settle lawsuit related to construction of the Streetcar approach ramp located near SE 2nd Ave and accept lump sum payment in the amount of $7,500,000

Emergency ordinance 192118Final official action · Portland.gov
Read the full official text

The City of Portland ordains.Section 1. The Council finds:The City, through its attorneys, filed a lawsuit against Tri-County Metropolitan Transportation District (TriMet) and Stacy & Witbeck, Inc. for damages arising from the construction of the Streetcar on-grade approach ramp located at SE 2nd Avenue.The City alleged breach of contract and negligence claims against the defendants.The City has concluded that after extensive analysis of the facts and applicable law, and taking into account the risks and uncertainties associated with litigation, the Settlement Agreement is desirable to avoid the time, risk, and expense of protracted litigation.The settlement provides a lump sum payment to the City. It also requires TriMet to provide additional support to the City to complete the repairs. Specifically, TriMet will assist the City in identifying and securing additional funding; TriMet will provide the City with technical assistance; and TriMet will provide service interruption assistance at no cost to the City if repairs are performed within the construction window for other contemplated repairs.The City Attorney, Portland Bureau of Transportation, and the Mayor's office recommend approval of the Settlement Agreement.NOW, THEREFORE, the Council directs:The Settlement Agreement is hereby approved and the Mayor or Mayor's designee is authorized to execute the Settlement Agreement on behalf of the City.Section 2. The Council declares that an emergency exists in order to avoid undue and costly delay in settling this lawsuit; therefore, this Ordinance shall be in full force and effect from and after its passage by the Council.

Meeting history1 meeting · 1 vote
About this recordSource checks & change history

0 human-reviewed findings are linked to this record. Unreviewed machine-extracted fragments are not presented as findings.

Technical information-completeness check · Ready With Caveats · Rules v2

This checks whether decision-relevant categories appear in the published packet. It does not recommend approval or opposition.

Decision definition

The official title and operative text identify the requested action.

Complete
Official legal text

Official text was found. This check does not certify that every referenced exhibit is complete.

Complete
Financial impact

The official impact statement includes financial information.

Complete
Funding source

The impact statement identifies funding information without an explicit unresolved-source qualifier.

Complete
Supporting documents

No linked attachments were found on the official page.

Unknown
Referenced exhibit integrity

No explicit exhibit reference was detected in the official text.

Not Applicable
Counterparty acceptance

The reviewed action is not expressly identified as a non-binding agreement.

Not Applicable
Implementation

A direction, reporting requirement, or deadline appears in the official text.

Complete
Document stability

Stability requires at least two observed snapshots; the system will update this after another ingestion.

Unknown
Source record
First discovered
Aug 13, 2026, 1:09 PM PDT
Last checked
Nov 13, 2026, 1:32 AM PST
Evidence hash
d091bc811bbfda6f
Guide status
Deterministic baseline
Append-only timeline
  1. SOURCE UPDATED

    Passed

  2. DOCUMENT PUBLISHED

    Observed in the official source.

  3. Council Action

    Passed

Independent guide by Portland Civic Lab. Official City records are authoritative. Votes alone do not establish a Councilor’s reasons.