Council approved a non-binding framework to renovate Moda Center and keep the Trail Blazers for at least 20 years. The binding contracts, complete funding plan, enforcement terms, and final community benefits still have to be negotiated.
Portland owns Moda Center. The building needs major systems and accessibility upgrades, and the Trail Blazers' long-term tenancy is tied to a renovation agreement.
On August 12 Council approved the term sheet 8 to 4. It authorizes negotiations but does not itself commit a specific funding source. The City, team, state, county, and arena authority still have to produce definitive agreements.
The central dispute is not simply whether Portland likes the Blazers. It is how financial risk, public return, labor standards, community benefits, rent, surrounding development, and enforcement should be allocated in a large public-private deal.
- Council vote
- 8 yes, 4 no on August 12, 2026
- Team commitment sought
- At least 20 more years of home games at Moda Center
- Current document
- A non-binding term sheet, not the final lease
- Return deadline
- Definitive agreements targeted by December 31, 2026