Authorize Bureau of Transportation to acquire certain temporary property rights necessary for construction of the SE Stark St: 111th - 151st Ave Project through the…
After the decisionFollow-through is not tracked yetA final vote is not the same as the work being done.
In brief
From the official impact statement
The City of Portland may exercise the power of eminent domain pursuant to Section 9-108 of the City Charter and in accordance with Eminent Domain procedures provided for in ORS Chapter 35 (Eminent Domain; Public Acquisition of Property), including those procedures that apply to notification, valuation, negotiation, relocation and early possession if necessary, when the exercise of such power is deemed necessary by the City Council to accomplish public purposes for which the City has responsibility.The City of Portland has the responsibility of providing safe transportation routes for commerce, convenience and to adequately serve the traveling public.The SE Stark St:…
PBOT carried out an 18-month public engagement process in 2019–20, gathering input through an online survey and in person discussions with community members along the Stark Street corridor. This outreach highlighted concerns about speeding, unsafe crossings, gaps in sidewalk and transit access, and the need for better visibility along the corridor. These priorities helped shape the project's focus on building safer pedestrian crossings and improving accessibility. PBOT continues to share updates and engage the public through community events and neighborhood meetings and encourages residents to sign up for notifications, and coordinates with neighbors and corridor stakeholders as the project advances.
Property values associated with the property rights acquisitions have not yet been quantified since negotiations are not completed; however, an estimate for the right of way phase has been budgeted in the Transportation Operating Fund. The level of confidence for the estimate is moderate. Funds are available in the General Transportation Revenue Fund 200000 Budget, FY 2026-2027 Budget, SAP # T01103.This legislation does not affect staffing levels or result in a new or modified financial obligation or benefit now or in the future.If City Council does not approve the ordinance, construction of the Project will not be feasible as planned, due to lack of property rights needed to make the improvements.
An Economic and Real Estate Development Impact Analysis was not submitted for this proposed action. Pursuant to City Council Resolution 37664, Prosper Portland staff has reviewed the action and agree that it does not require an Economic and Real Estate Development Impact Analysis.
Vote register entry for 2026-335: Authorize Bureau of Transportation to acquire certain temporary property rights necessary for construction of the SE Stark St: 111th - 151st Ave Project through the exercise of the City’s Eminent Domain Authority
3 files of 3 posted to this record have a plain summary. 17 factual statements were compared with the rest of the record. None differs from another official passage. 10 match another document. 1 cites an outside source. 6 name no source.
This Public Works Committee staff summary describes an ordinance authorizing the City to acquire temporary property rights for intersection improvements. The summary says the City can negotiate payment for those rights and seek a court decision if negotiations fail. It records a committee recommendation to pass the ordinance.
4 matches the record
1 cites an outside source
2 no source given
Read the 7 statements checked
Matches the record
The summary says safety improvements at SE 119th Avenue and SE Stark Street require temporary permission to use property for construction.
The file says
Safety improvements at the intersection of SE 119th Avenue and SE Stark Street require a temporary
construction easement.
Easement acquisitions are required from two (2) property owners,
consisting of two (2) temporary construction easements that will
support construction activities.
The summary says the current safety plan phase includes pedestrian crossing improvements at six intersections with higher crash history.
The file says
The current phase of the Safer Outer Stark safety plan includes pedestrian crossing improvements at six
intersections with higher crash history: SE 111th and Stark; SE 119th and Stark; SE 128th and Stark; SE 137th
and Stark; SE 141st and Stark; and SE 151st and Stark.
PBOT was awarded a grant through the ODOT All Roads Transportation Safety (ARTS)
Program as part of the 2024-2027 funding cycle to address high incidence of pedestrian
and turning crashes on SE Stark between SE 108th and SE 162nd.
Project scope for this ARTS project includes enhanced pedestrian crossings at six key
intersections on SE Stark (SE 111th, 119th, 128th, 137th 141st and 151st).
No source is named in the file. This does not mean the statement is wrong.
Matches the record
The summary says planned construction includes accessible curb ramps, pedestrian crossing islands, improved signs and striping, and drainage and utility updates.
The file says
At these intersections, the Portland Bureau of
Transportation will construct ADA compliant curb ramps, pedestrian crossing islands, enhanced signing
and striping, and updated drainage and utility components.
The SE Stark St: 111th - 151st Ave Project (the "Project") will construct improved ADA compliant curb ramps, pedestrian crossing islands, enhanced signing and striping, and updated drainage and utility components.
The summary says the City can exercise eminent domain under Section 9-108 of the City Charter using procedures in Oregon Revised Statutes (ORS) Chapter 35.
The file says
The City is
authorized to exercise the power of eminent domain under Section 9-108 of the City Charter and in
accordance with the procedures outlined in Oregon Revised Statutes (ORS) Chapter 35.
The City of Portland may exercise the power of eminent domain pursuant to Section 9-108 of the City Charter and in accordance with Eminent Domain procedures provided for in ORS Chapter 35 (Eminent Domain; Public Acquisition of Property), including those procedures that apply to notification, valuation, negotiation, relocation and early possession if necessary, when the exercise of such power is deemed necessary by the City Council to accomplish public purposes for which the City has responsibility.
This transportation presentation describes pedestrian crossing improvements at six intersections on SE Stark. The slides list a $2.3 million project budget and construction starting in spring 2028. They say PBOT seeks temporary construction easements from two (2) property owners, with condemnation possible if negotiations fail.
4 matches the record
4 no source given
Read the 8 statements checked
No source given
The slides list a $2.3 million total project budget, including $1.3 million in federal funding and $1.0 million in local funding.
The file says
Federal (ODOT ARTS Grant): $1.3 million
Local Funding (GTR, FOS): $1.0 million
Total Project Budget: $2.3 million
The slides say the project includes enhanced pedestrian crossings at six intersections on SE Stark.
The file says
Project scope for this ARTS project includes enhanced pedestrian crossings at six key
intersections on SE Stark (SE 111th, 119th, 128th, 137th 141st and 151st).
The current phase of the Safer Outer Stark safety plan includes pedestrian crossing improvements at six
intersections with higher crash history: SE 111th and Stark; SE 119th and Stark; SE 128th and Stark; SE 137th
and Stark; SE 141st and Stark; and SE 151st and Stark.
No source is named in the file. This does not mean the statement is wrong.
No source given
The slides say PBOT received an ODOT All Roads Transportation Safety (ARTS) Program grant in the 2024-2027 funding cycle to address pedestrian and turning crashes.
The file says
PBOT was awarded a grant through the ODOT All Roads Transportation Safety (ARTS)
Program as part of the 2024-2027 funding cycle to address high incidence of pedestrian
and turning crashes on SE Stark between SE 108th and SE 162nd.
PBOT carried out an 18-month public engagement process in 2019–20, gathering input through an online survey and in person discussions with community members along the Stark Street corridor. This outreach highlighted concerns about speeding, unsafe crossings, gaps in sidewalk and transit access, and the need for better visibility along the corridor.
The exhibits give legal descriptions of temporary construction easements for the Stark Street project. They describe one area of 65 square feet and another of 63 square feet.
Only 2 of 4 pages had readable text. Scanned pages were not checked.
2 matches the record
Read the 2 statements checked
Matches the record
The exhibit lists a temporary construction easement covering 65 square feet.
Compared with the record page and the City's analyses, Committee Staff Summary, Presentation.
How to read these labels
Matches the record
Another official document on this record says the same thing. That shows the documents agree. It does not show the statement is true, and the two documents may come from the same office.
Conflicts with the record
Another official passage on this record says something different. Both passages are shown. This site does not decide which one is right.
Differs from its cited source
The document attributes the statement to a source on this record, and that source reads differently. Both passages are shown.
Cites an outside source
The document names a source that is not part of this record. This site has not checked that source.
No source given
The document does not say where the statement comes from, and the record documents this check read do not address it. This does not mean the statement is wrong.
Summaries and labels are written by software and checked by a second automated pass. No person reviewed them before publication. Each label rests on the quoted passages shown with it, and compares a file only with the other official documents on this record. Written testimony from residents is not checked. Every version, including replaced and withdrawn ones, stays public.
Official title: Authorize Bureau of Transportation to acquire certain temporary property rights necessary for construction of the SE Stark St: 111th - 151st Ave Project through the exercise of the City’s Eminent Domain Authority
First seen is when this site’s hourly check found a file. The City may have posted it up to an hour earlier. Read the full official text
The City of Portland ordains.Section 1. The Council finds:The City of Portland may exercise the power of eminent domain pursuant to Section 9-108 of the City Charter and in accordance with Eminent Domain procedures provided for in ORS Chapter 35 (Eminent Domain; Public Acquisition of Property), including those procedures that apply to notification, valuation, negotiation, relocation and early possession if necessary, when the exercise of such power is deemed necessary by the City Council to accomplish public purposes for which the City has responsibility. The City of Portland has the responsibility of providing safe transportation routes for commerce, convenience and to adequately serve the traveling public. The project known as the SE Stark St: 111th - 151st Ave Project (the Project) has been planned in accordance with appropriate engineering standards for the construction, maintenance, or improvement of said transportation infrastructure such that property damage is minimized, transportation promoted, and travel safeguarded. The Project will upgrade safety along the corridor by constructing improved ADA‑compliant curb ramps, pedestrian crossing islands, enhanced signing and striping, and updated drainage and utility components. For this segment at SE 119th Ave. and SE Stark St., the project will build new ADA curb ramps and a pedestrian refuge island to provide a safer, more accessible crossing for community members. To accomplish the Project set forth above, it is necessary to acquire the following property interests described and depicted in Exhibits 1 through 4, attached to this Ordinance, and by this reference incorporated herein. All affected property owners have been contacted and informed as to the City's need for certain property rights related to completion of the Project. All affected property owners have been invited by certified mail to attend the reading of this agenda item. Funds are available in the General Transportation Revenue Fund 200000. NOW, THEREFORE, the Council directs:That it is hereby declared that it is necessary to acquire the property interests described and depicted in Exhibits 1 through 4 to this Ordinance for the Project, for which the City is authorized by law to acquire property, and that the Project has been planned, designed, located, and will be constructed in a manner which will be most compatible with the greatest public good and the least private injury.That the City Administrator or designee and/or City Attorney are authorized to acquire necessary temporary rights for the Project under the Eminent Domain Authority of the City, including filing an action to acquire the property interests described herein or negotiating just compensation with property owners within available project budget funds.That the power of eminent domain is hereby exercised with respect to each of the interests in property described and depicted in Exhibits 1 through 4. Each is acquired subject to payment of just compensation and subject to procedural requirements of Oregon law.That the Bureau of Transportation's staff and the Office of the City Attorney are authorized to attempt to agree with the owner and other persons in interest as to the compensation to be paid for each acquisition, and, in the event that no satisfactory agreement can be reached, to commence and prosecute such condemnation proceedings as may be necessary to finally determine just compensation or any other issue appropriate to be determined by a court in connection with the acquisition. This authorization is not intended to expand the jurisdiction of any court to decide matters determined above or determinable by the City Council.That the Bureau of Transportation is authorized to determine the continuing necessity or propriety of the acquisition authorized by this Ordinance, its quantity, quality, or locality, and to reduce or abandon any acquisition described in Exhibits 1 through 4.There is hereby authorized the creation of a sub-fund in the amount estimated to be the just compensation for each interest in the property which, if necessary, shall be deposited with the clerk of the court where an action is commenced.
Meeting history3 meetings · 2 votes
PassedAgenda item 11
Passed to second readingAgenda item 6
Passed to second reading October 7, 2026 at 9:30 am
Referred to City CouncilAgenda item 4
Motion to refer the Ordinance, Document Number 2026-335, to City Council with the recommendation it be passed: Moved by Koyama Lane and seconded by Smith. (Aye (4): Koyama Lane, Smith, Kanal, Clark; Absent (1): Green)
Read all 1 exact motions
Sep 22, 2026 · Main · Passed
Motion to refer the Ordinance, Document Number 2026-335, to City Council with the recommendation it be passed: Moved by Koyama Lane and seconded by Smith. (Aye (4): Koyama Lane, Smith, Kanal, Clark; Absent (1): Green)
Motion to refer the Ordinance, Document Number 2026-335, to City Council with the recommendation it be passed: Moved by Koyama Lane and seconded by Smith. (Aye (4): Koyama Lane, Smith, Kanal, Clark; Absent (1): Green)
0 human-reviewed findings are linked to this record. Unreviewed machine-extracted fragments are not presented as findings.
Technical information-completeness check · Ready With Caveats · Rules v2
This checks whether decision-relevant categories appear in the published packet. It does not recommend approval or opposition.
Decision definition
The official title and operative text identify the requested action.
Complete
Official legal text
Official text was found. This check does not certify that every referenced exhibit is complete.
Complete
Financial impact
The official impact statement includes financial information.
Complete
Funding source
The impact statement identifies funding information without an explicit unresolved-source qualifier.
Complete
Supporting documents
3 linked supporting documents found; presence alone does not verify their internal completeness.
Complete
Referenced exhibit integrity
The text references exhibits. This guide has not yet automatically verified that each referenced exhibit is present, populated, and internally consistent.
Unknown
Counterparty acceptance
The reviewed action is not expressly identified as a non-binding agreement.
Not Applicable
Implementation
A direction, reporting requirement, or deadline appears in the official text.
Complete
Document stability
Stability requires at least two observed snapshots; the system will update this after another ingestion.
Unknown
Source record
First discovered
Oct 7, 2026, 12:07 PM PDT
Last checked
Nov 11, 2026, 3:07 PM PST
Evidence hash
99ce63479f2227c6
Guide status
Deterministic baseline
Append-only timeline
SOURCE UPDATED
Passed
Council Action
Passed
SOURCE UPDATED
Passed to second reading on September 30, 2026 by City Council
Council Action
Passed to second reading
SOURCE UPDATED
Referred to City Council on September 22, 2026 by Public Works Committee
Council Action
Referred to City Council
SOURCE UPDATED
Referred to Public Works Committee by Council President
DOCUMENT PUBLISHED
Referred to Public Works Committee by Council President
Independent guide by Portland Civic Lab. Official City records are authoritative. Votes alone do not establish a Councilor’s reasons.